From: route@monster.com
Sent: Friday, April 08, 2016 12:14 PM
To: hg@apeironinc.com
Subject: Please review this candidate for: p6 PMP
This resume has been forwarded to
you at the request of Monster User xapeix03
|
|||||||
|
|||||||
|
|
|
||||||
|
||||||
|
CYRIAC ABRAHAM
MSE, CCP, PMP 16502 Lake Medina Way, Houston, TX 77044 Res: (281)
436 0972 * Cell: (713) 240 1409 * abrahamcyriac@aol.com Project
delivery on budget and schedule – Guaranteed! Innovative and detail oriented Project Planning
& Scheduling Leader for multi-billion $ projects o Proactive
leadership in project planning, estimating, WBS development and detailing,
budgeting and cost allocation, aligning WBS and CTR with Cost Breakdown
Structure, developing OBS and RACI matrix o Expertise
in CPM schedule logic networks; resource estimating, loading & leveling;
and optimizing total float o Ability to
visualize and manage large project data from drawings, specifications,
meetings, and reports and to correlate with schedule activities and their dependencies
for greenfield, brownfield, and turnaround projects o Instrumental
in turning around delayed $1.2 billion project schedule; completed project
before contract. o Performed
delay analysis; created turnaround schedule; saved multimillion $ by
initiating timely solutions o Leader
with focus on project closeout from Day 1; always accommodates project risks
in schedule o
Expert in Deliverable Based Schedules (Startup Systems
approach) which help to focus resources on critical activities and priorities
resulting in timely project completion and significant cost savings Expert Primavera user - in the planning, scheduling
& cost control of large, complex projects o Implemented
resource & cost loaded Primavera schedules (15,000+ activities) for award
winning projects* o Performed
critical path analysis, schedule risk analysis, schedule simulations, and
schedule-cost optimization o Provided
Primavera P6 training and support to team members of projects in US and
abroad. o Created
Code of Cost Accounts and tracked costs; developed performance metrics,
models for reports, analysis, and charts; successfully forecasted completion
dates and Estimate at Completion (EAC) o
Proactively verified and validated project assumptions and
initiated change management to avoid delays Leadership for Project Controls teams o Successfully
developed and managed Project Controls teams for large projects and startup
companies o Developed
and implemented Project Controls objectives, policies, processes, and systems o Authored
Project Controls Management Plans; developed schedule templates, performance metrics, and models for
reports, analysis, and charts; produced periodic cost and schedule reports;
accurately forecasted project outcomes Hands-on knowledge of construction practices o More than
15 years’ field experience in the construction of refineries, pipelines,
chemical plants, power plants o Thorough
knowledge of construction materials and processes: concrete and steel
structures; ferrous and non-ferrous pipes and pipe fittings; rotating and
static equipment; columns and vessels; storage tanks; thermal insulation;
electrical cables and machinery; instrumentation & controls; paint and
corrosion prevention. o Hands-on
experience in prefabrication, erection, quality control, field testing,
start-up & commissioning o
Project Management: Constructability, Preconstruction,
planning, scheduling, cost control, EV, & risk control Diversity in Projects o Successfully
managed all contract types – Fixed-Price, Cost-Plus, and Unit-Price o Several
contracting methods - Prime, Multi-Prime, Job Order; Various scopes –
Pre-FEED, FEED, EPC, PM o Diverse
geography and culture: USA, Canada, Saudi Arabia, Kuwait, Libya, India o
Various clients: Alyeska Pipeline, B&W, BP, CF Braun
& Co., Eni, ExxonMobil, Panda Funds, Shell, TECO Industry Award Winning Projects o Senior
Project Controls Engineer of Panda Gila River (CCGT) Power Station Project at
Gila Bend, AZ which received “Excellence in Construction” Award from
Associated Builders and Contractors (ABC) o
Lead Project Scheduler of 500 MW Weston 4 Project in
Wausau, WI which received Best Coal-Fired Project by Power Engineering
magazine; Power Magazine's 2008 Power Plant of the Year, and Platts Global
Energy Finalist in Construction Project of the Year Personal
Best Award for outstanding
contribution for revised baseline schedule, SNC-Lavalin Constructors,
Inc. ___________________________PROFILE__________________________________ MSE (Master of Science in Engineering), Purdue
University; BSEE, Electrical Engineering, NIT, Calicut, India CCP
(Certified Cost Professional), AACE International, USA PMP
(Project Management Professional), Project Management Institute,
USA Expert in
Primavera Project Management 6.0 (P6), Milestone Professional, Primavera Cost
Manager; MS Office 2010 Proficient in
Timberline, Prolog, MS Project, SAP, Oracle, RS Means Costworks, Pertmaster US Citizen __________________________PROFESSIONAL EXPERIENCE__________________________ Principal
Planning & Scheduling Consultant, Growtech
Partners, Houston
(2010 to July 2015) *
Provided leadership and oversight for development of construction schedule
and integrating with engineering, procurement, and startup (by others) of a
multi-billion $ LNG Project in TX. Modified and improved the schedule and won
client and third party consultant’s confidence for baseline approval. *
Provided project schedule analysis using Primavera P6 for dispute resolution
for a power sector client to estimate and recover losses due to owner caused
delays. Performed variance analysis, calculated cost escalations, and impact
on profit. Worked with attorneys and got 90% of claims successfully
established. *
Implemented Project Controls for Panda Funds, Dallas with multi-billion $
investments in natural gas power plants; advised on developing and
implementing schedule management from an owner perspective. Special areas of
focus were budgeting, cost control, owner schedule interfaces; contractor schedule review and
evaluation. Facilitated change management, maintained and updated project
risk register, and evaluated impacts. Developed tools to analyze variances
and forecast Estimate at Completion and delivery of project milestones. *
Implemented Integrated Activity Planning for a global energy company (Shell)
for their multi-billion $ shale gas exploration program in PA, USA. Developed
resource loaded Integrated Activity Planning schedule for 2011, 2012 and 2013
programs. Established cost codes, budgets, value of work done metrics,
schedule included permitting (FERC guidelines), logistics, construction,
drilling, well completions and intervention, flowback, operations, pipeline
systems. * Prior to this served as Project
Management Consultant and Subject Matter Advisor to Accenture Consulting for
their Capital Project Management group; advised on implementation of PMO for
3 billion USD 4x660 MW TSPL Project in Punjab, India. Performed independent
verification and validation of EPC project schedule; advised on development
and implementation of resource loaded recovery schedule for the delayed
project Reviewed project execution plan, schedule, critical path, contracting
strategy, organizational structure,
RACI Matrix, resource planning, resource availability, and project risk
management; made recommendations for project cost optimization. Recommended a
new methodology to bridge gap between planning, scheduling and actual work;
provided training to TSPL and Accenture employees on schedule and cost
management, and Primavera P6 scheduling tool. Project
Controls Leader, CH2M HILL Alaska,
Anchorage, AK
(2008 – 2010) Worked with various operators in Alaska
including North Slope – BP, Eni, ConocoPhillips. Reviewed planning and
scheduling efforts at BP’s OTL28 and OTL50 Pipeline Programs; converted BP
Liberty Project schedule from discipline based to startup system based.
Supervised development and implementation of project schedule for Eni’s
Nikaitchuq Onshore Process & Drilling Facilities at North Slope, AK
Developed startup system based schedule, established KPIs, implemented earned
value method for measuring project progress in labor-hours, tracked project
actual labor-hours against budget labor-hours to update schedule; managed
changes; facilitated Primavera P6 training courses 102 and 106 to company
employees multiple times and won 90% customer satisfaction. Performed as
scheduling expert on various bids ranging from 5 million to 125 million USD;
reviewed project assumptions and calculations; validated estimate basis; evaluated
risks and contingencies Participated in contractor selection and bid
evaluations; reviewed contractor bid schedules, verified milestones, logic,
resource planning, assumptions, risks, etc. Developed models for project
execution plans, project status reports, analysis and charts; developed and
streamlined change management workflows. Visited projects and resolved
schedule, and other project controls issues Submitted “Project Controls
Processes and Systems Improvement Proposal” which was recommended by senior
management for implementation for improved project controls performance;
played an active role in Construction Excellence Initiative. Assisted Human
Resources to identify, select, and interview candidates for adding to Project
Controls team. Project
Controls Manager / Lead
Scheduler, Bechtel Corporation,
Houston, TX
(2007 –2008) Participated in development of WBS;
developed CTR based schedule and Earned Value of 3 MTPA PNG-LNG Pre-FEED
Project, and 3 MTPA Santos Gladstone LNG Pre-FEED Project; coordinated
Engineering, Procurement, Construction, and Startup for Pre-FEED, FEED and
EPC schedules; produced weekly and monthly project performance reports based
on schedule and cost; prepared analysis and charts for project management,
corporate and client review; highlighted issues, areas of concerns,
variances, risks, opportunities, and recommended solutions. Developed
staffing plans based on schedule; created templates for charts and reports;
documented estimate basis and project assumptions; monitored schedule and
performance factors; reviewed actual labor-hours and productivity; tracked
project costs; contributed to Project Controls Execution Plan, proposal
budget and schedule. Also, reviewed and modified FEED schedule and EPC
schedule for Brass LNG Project. Reviewed JV partner schedules. Director,
Project Controls & Planning, Noble
Environmental Power, LLC, Essex, CT
(2006 – 2007) Developed and implemented “Total Cost
Management” based project control systems for the $ 1.3 billion CapEX program
of the renewable energy (wind) startup company. Authored project controls
policies, procedures and daily work instructions for cost & schedule
engineers; established project cost, schedule and Earned Value measurement
and reporting guidelines. Developed Code of Accounts; established interfaces
& procedures with other departments for project cost and schedule data
transfer. Created models for reports, analysis and charts to represent
project cost, schedule and earned value. Developed project specific Terms
& Conditions for contract bid packages; identified roles &
responsibilities for project services and project controls functions;
participated in contractor selection and evaluated contractor bids; established
contractor back charge process. Supervised estimation of project quantities
and resources, budget development, resource and cost allocation, schedule
development and update process, progress tracking – quantities installed;
change management and earned value reports. Established Schedule of Values,
rules of credit, thresholds for variances; conducted field audits to verify
quality of reporting. Implemented document control system using Primavera
Expedition Reviewed, compared and countered contractor pricing. Hired and
trained project control personnel. Supervised project controls companywide;
administered Primavera Expedition and P6.0 DB. Lead
Scheduler, Washington Group
International, Boise, ID
(2004 –2006) Developed project WBS; designed,
developed and maintained the 15,000-activity EPC CPM Integrated Project
Schedule of $752 million, 500 MW Weston-4 Power Project, at Wausau, WI.
Coordinated more than 50 vendors and contractors through schedules; managed
multi-party interfaces; supervised weekly updates and reports Defined
baseline approval process; the minimum requirements and protocols for
electronic import of Primavera contractor schedule data into owner’s IPS.
Reviewed and approved contractor baseline schedules; verified logic, resource
planning, constraints, etc. Established procedures for day-to-day business of
scheduling department; provided technical guidance for scheduling & P3e/c
to project team and contractors. Coordinated multiple project schedulers;
conducted weekly meetings to review schedule, earned value, and critical
path; analyzed variances, recommended corrective actions. Senior
Project Controls Engineer, SNC-Lavalin
Constructors Inc, Bothell,
WA
(2001 –2003) Managed USD 1.2 billion budget and 10,000
activity P3 schedule of 2,400 MW combined cycle power plant project in
Arizona; 599 MW Combined Cycle Power Project at McAdams, MS. Developed WBS
and resource and cost loaded EPC project schedule. Monitored contractor
schedule updates; tracked quantities installed and evaluated value of work
done and work-in-progress; conducted periodic cost and schedule review
meetings; discussed critical path, schedule & variances; generated management
reports and appraised project manager and client; recommended corrective
solutions Some of the projects Cyriac Abraham
worked on (from field / home office): LNG
/ SHALE GAS *
3 MTPA PNG-LNG Pre-FEED Project (Papua New Guinea) *
3 MTPA GLNG Pre-FEED Project (Santos Gladstone, Australia) *
6 MTPA Brass LNG-FEED Project (Nigeria) *
20 MTPA Freeport LNG Project, Quintana, TX * Shale Gas Development Program of Shell
in Appalachia, PA, USA OIL/GAS/PIPELINE *
Nikaitchuq Onshore Process & Drilling Facilities, Eni, North Slope,
Alaska *
Liberty Drill Rig Project at North Slope, Alaska for BP *
Oil Transmission Pipeline Projects (OTL 28 and OTL 50) at Prudhoe Bay, Alaska
for BP (Turnaround) *
Strategic Reconfiguration Project (SRP) of Alyeska Pipeline Service Company,
North Slope, Alaska (Turnaround) * Safaniya Onshore Gas Gathering
Facilities for Aramco at Safaniya, Saudi Arabia REFINING *
240,000 BPD Mina Abdullah Refinery Modernization Project, Kuwait *
Hydro-cracker and H2 Units for 3 MTPY Numaligarh Refinery, Assam, India *
Catalytic reformer Units for Digboi Refinery, Assam, India (Turnaround) * Catalytic reformer Units for Barauni
Refinery, Bihar, India (Turnaround) CHEMICAL
/ FERTILIZER *
900 MT Urea Plant for National Fertilizers Ltd., Bhatinda, India *
Project Tiger (integrating a new esterification system) for INVISTA at
Spartanburg, SC (Turnaround) *
Technology Conversion Project for Canexus at Vancouver, Canada (Turnaround) * Mavoor Gwalior Rayons at Calicut,
Kerala, India (Turnaround) |
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Languages: |
Languages |
Proficiency Level |
|
English |
Fluent |
|
|
|